Kennedy Boulevard, from All American Boulevard to Wymore Road, will be widened from 2 to 4 lanes. Pedestrian safety will also be improved with the addition of sidewalks and bike lanes. Roadway lighting and median landscaping will also be included.

The project will be completed in 2 phases:

-Segment 1: The Forest City Road intersection, is to be constructed with the new All American Boulevard Roadway project.

-Segment 2: East of the Forest City Road intersection to Wymore Road will be completed as part of the INVEST initiative.

Additionally, the impacts resulting from the realignment of Lake Destiny Drive will be determined.

Purpose

This roadway widening will provide additional capacity to improve the level of service.

Status

Segment 1 is currently in procurement phase.

Segment 2 is in right-of-way acquisition.

Timeframe

Segment 1 ( W of Forest City Rd to Kingstone Ct.): construction scheduled for late 2025.

Segment 2 ( King Stone Ct. to Wymore Rd): construction is unfunded.

Public Involvement

Newsletters will be distributed when the project is advertised for construction bids.

Contact Us

Hadil Jardaneh, Senior Engineer
Orange County Engineering
4200 S. John Young Parkway
Orlando FL 32839

Email: Hadil.Jardaneh@ocfl.net
Phone: 407-836-8083